The timeline for a completed Groveland Community Trail is upwards of ten years. 

 

Many factors influence this type of shared-use path projects, including various design aspects, state & federal funding approval processes, and most importantly, Town & resident consensus.

 

Below is an estimated timeline for the Groveland Community Trail project.  Note: any and all estimates are subject to change.

Estimated project timeline

Complete 100% MassDOT-ready design plan for on-road trail segment

Construction of the

Groveland Communtiy Trail

Complete initial feasibilty study

Complete 100% MassDOT-ready design plan for off-road trail segment

Request additional CPA dollars to complete 100% MassDOT design plan for on-road trail segment

Estimated 1H 2016

2016 Town Meeting

Estimated by 1H 2017

Estimated 2018 or after

Completed 2012

Voters pass at April 2014 Annual Town Meeting

Town Meeting vote to commit CPA funds for conceptual design

January 2015

Complete 25% MassDOT-ready design  plan for off-road trail segment

December 31 2014

Complete 10% design plan for on-road trail segment

Select engineer partner via a public and competitive RFP process

August 2014

August 2014

Confirm clear title on off-road trail segment, the utility corridor owned and operated by National Grid

January 2015

Proposal due for requested  CPA warrant for 2015  Town Meeting

Estimated 2017/2018

Gain approval for construction funding from MassDOT for on-road trail segment

Estimated 2017 or after

Complete required license agreement with National Grid